Riverside sewer district

Riverside sewer district design 60% complete, town says system would serve homes by 2030

by Apr 30, 2026
Southampton Town gave Riverside residents a closer look at the $44 million sewer district planned for the hamlet, including grinder pumps at each property, projected user costs and a timeline that could bring the system online in late 2029 or early 2030.

Riverside wastewater treatment facility update meeting set for April 29

by Apr 14, 2026
The Town of Southampton will host a community discussion of the Riverside Water Resource Recovery Facility on Wednesday, April 29 at 7 p.m. at the Flanders Community Center, 655 Flanders Road, Flanders.

Judge throws out Riverhead lawsuit against Southampton over Riverside sewer district

by Oct 8, 2025
Riverhead's ultimate goal was to have the new Riverside Sewer District treat wastewater from the county complex in Riverside, which the Riverhead Sewer District has been handling since 1969.

Downtown Riverhead developer eyes Riverside site for 40 affordable apartments, shops

by Jul 11, 2025
The developer of the Riverview Lofts apartment building in downtown Riverhead has proposed a 40-unit rental apartment complex with ground-floor retail space in Riverside.

Southampton official: Town will build Riverside sewer plant despite ‘$5 million shortfall’ after Congressional funding requests scrapped

by Mar 18, 2025
The stopgap funding measure enacted this weekend does not contain any congressionally directed spending for fiscal year 2025, including a $5 million grant submitted by Senate Minority Leader Chuck Schumer for the Riverside sewer district facility.

FY 25 budget measure omits congressional earmarks, affecting $19M in funding requests for local projects

by Mar 17, 2025
The nearly $1.7 trillion funding bill keeps the federal government operating through Sept. 30 eliminated all member "earmarks" for specific projects.

Riverhead Town authorizes lawsuit against Southampton, hoping to stop sewer plant in Riverside

by Jul 10, 2024
Riverhead Town has retained an attorney to sue the Town of Southampton over its proposed sewer district for the hamlet of Riverside — a facility that is essential to developing mixed-use housing in the hamlet, as called for by a plan approved by Southampton nearly a decade ago.

Phillips Avenue teachers plan demonstration Tuesday to protest new sewage plant site

by Jun 24, 2024
Teachers at Phillips Avenue Elementary School are planning to demonstrate outside the school tomorrow to raise concerns about Southampton Town’s plan to site a sewage treatment plant in Riverside near the school.

Riverhead gears up to sue Southampton, as two towns remain at odds over Riverside revitalization plan and sewer district

by Apr 12, 2024
Trouble is brewing between the two towns that straddle the Peconic River. The bone of contention: Southampton Town’s plan for revitalization of the Riverside hamlet, adopted nearly 10 years ago.

Riverhead supervisor makes pitch to Southampton Town: Let’s partner to revise Riverside redevelopment plan

by Jan 25, 2024
Supervisor Tim Hubbard offered Southampton officials Riverhead’s help to revise its Riverside development plans, including partnering on a market and demographic study. He also asked that the proposed Riverside sewer district take in the county facilities there.