Riverhead Solar 2 hearings postponed after developer opts to transfer application to new renewable energy siting office

by
Hearings scheduled today before the Electric Generating Siting Board have been postponed because Riverhead Solar 2 has filed notice that it intends to transfer its application to a new state office created to expedite approvals of renewable energy projects.

State to hold virtual public hearings Tuesday on proposed 36-MW solar facility in Calverton

by
The NYS Board on Electric Generation Siting and the Environment will hold virtual public hearings Tuesday at 1 p.m. and 6 p.m. on the proposal of sPower to build a 36-megawatt solar power facility on approximately 252 acres in Calverton. People interested in making a statement must register by Friday at 5 p.m.

Riverhead officials seek moratorium on new commercial solar facilities

by
Riverhead Town is considering a 12-month moratorium on new commercial solar energy production facilities. The moratorium would not affect the two applications for major solar production facilities currently pending for some 488 acres of land in Calverton.

Riverhead Solar 2 public information session to take place this evening

by
There will be a virtual public information session this evening about sPower’s proposed 36MW solar power facility in Calverton.

Riverhead to gain $1.05 million in ‘community benefit’ funding from solar energy producer

by
The funds are earmarked for agriculture and open space protection, environmental protection, health and welfare and education/employment.

Town will see nearly $1.5 million in deal with solar power company

by
sPower will pay Riverhead Town a $1.05 million community benefit fee and a $450,000 easement fee, in addition to an annual payment in lieu of taxes that will start at $460,000 in year one and increase each year for 15 years.

State officials to discuss town’s funding request for sPower application review: Conference set in Riverhead Nov. 8

by
A pair of state administrative law judges will hold a conference on Riverhead Town's request for $12,600 in funding to defray the cost of reviewing sPower's Riverhead Solar-2 application.

Riverhead Planning Board cries foul, requires new environmental review for already-approved sPower solar facility

by
“In my opinion, this is a lack of information-sharing by sPower and possible willful misrepresentation with intent to deceive,” Planning Board Chairman Stan Carey said, citing sPower's representations that an underground tie-line would be used only for the 20MW solar facility approved by the town earlier this year. Now the company wants to use the same tie-line for a new 36 MW facility being reviewed by the state.

State begins review of 290-acre 36 MW solar power facility proposed for Calverton

by
A 36 MW solar power generation facility on 290 acres of leased vacant land in Calverton is now under review by the a facility siting board of the State Department of Public Service, which has sole jurisdiction over the application. But the Town of Riverhead may reopen environmental review of a previously approved 20 MW facility proposed by the same company so that the impacts of both facilities may be examined.

Solar power developer to host open house today about the 36 MW facility it plans for 275 acres of ag lands...

by
The public informational meetings will take place today in two sessions, from 1 to 3 p.m. and from 5 to 7 p.m. at the Residence Inn located at 2012 Old Country Road, when company representatives will explain the project’s details, answer questions and receive public comment.